docs(02-03): complete human verification — phase 2 approved
- All 7 checklist items approved by human reviewer - Visual fixes applied: hero objectPosition 20%, contact form white inputs, testimonial gold accent bar - Phase 2 marketing site marked complete (MKTG-01 through MKTG-04 satisfied) - STATE.md updated: phase 2 complete, 6/6 plans done, progress 40%
This commit is contained in:
@@ -6,9 +6,9 @@ status: unknown
|
||||
last_updated: "2026-03-19T21:03:39.146Z"
|
||||
progress:
|
||||
total_phases: 2
|
||||
completed_phases: 1
|
||||
completed_phases: 2
|
||||
total_plans: 6
|
||||
completed_plans: 5
|
||||
completed_plans: 6
|
||||
---
|
||||
|
||||
# Project State
|
||||
@@ -22,12 +22,12 @@ See: .planning/PROJECT.md (updated 2026-03-19)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 2 of 7 (Marketing Site)
|
||||
Plan: 2 of 3 in current phase (02-01 and 02-02 complete)
|
||||
Status: In progress
|
||||
Last activity: 2026-03-19 — Plan 02-01 complete: Marketing site shell — sticky nav, hero, testimonials carousel, listings placeholder, footer
|
||||
Phase: 2 of 7 (Marketing Site) — COMPLETE
|
||||
Plan: 02-03 complete (all 3 plans in phase complete)
|
||||
Status: Phase 2 complete — awaiting Phase 3 start
|
||||
Last activity: 2026-03-19 — Plan 02-03 complete: Human verification approved all 7 checklist items; Phase 2 marketing site complete
|
||||
|
||||
Progress: [███░░░░░░░] 24%
|
||||
Progress: [████░░░░░░] 40%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
@@ -88,5 +88,5 @@ None yet.
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-03-19
|
||||
Stopped at: Completed 02-02-PLAN.md — Contact form: Nodemailer SMTP mailer, Server Action with Zod+honeypot, ContactSection client component
|
||||
Stopped at: Completed 02-03-PLAN.md — Human verification approved; Phase 2 marketing site complete with visual fixes (hero objectPosition, contact field styling, testimonial accent bar)
|
||||
Resume file: None
|
||||
|
||||
Reference in New Issue