gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
status: unknown
last_updated: "2026-03-19T21:03:39.146Z"
progress:
total_phases: 2
completed_phases: 1
total_plans: 6
completed_plans: 5
---
2026-03-19 12:25:02 -06:00
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-03-19)
**Core value:** Teressa can prepare and send any real estate form to a client for signing in minutes, from her browser, without leaving her site.
**Current focus:** Phase 2 - Marketing Site
2026-03-19 12:25:02 -06:00
## Current Position
Phase: 2 of 7 (Marketing Site)
Plan: 2 of 3 in current phase (02-01 and 02-02 complete)
Status: In progress
Last activity: 2026-03-19 — Plan 02-01 complete: Marketing site shell — sticky nav, hero, testimonials carousel, listings placeholder, footer
2026-03-19 12:25:02 -06:00
Progress: [███░░░░░░░] 24%
2026-03-19 12:25:02 -06:00
## Performance Metrics
**Velocity:**
- Total plans completed: 2
- Average duration: 4 min
- Total execution time: 0.1 hours
2026-03-19 12:25:02 -06:00
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| 01-foundation | 2/3 | 8 min | 4 min |
| 02-marketing-site | 2/3 | 8 min | 4 min |
2026-03-19 12:25:02 -06:00
**Recent Trend:**
- Last 5 plans: 01-01 (6 min), 01-02 (2 min), 02-01 (4 min), 02-02 (4 min)
- Trend: stable
2026-03-19 12:25:02 -06:00
*Updated after each plan completion*
| Phase 02-marketing-site P01 | 5 | 2 tasks | 8 files |
2026-03-19 12:25:02 -06:00
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table.
Recent decisions affecting current work:
- Custom e-signature over DocuSign: lower ongoing cost for solo agent; full brand control
- Next.js full-stack: single repo for marketing + web app via API routes
- Email-link signing (no client account): lowest friction for clients; standard in real estate
- utahrealestate.com forms scraping: AVOID — violates ToS; use manual PDF upload instead
- Infrastructure: local PostgreSQL (Docker) + local `npm run dev`; no Vercel, no Neon, no cloud storage — home Docker server is eventual target
- [Phase 01-foundation]: Lazy Proxy singleton for db/index.ts prevents neon() crash during Next.js build when DATABASE_URL absent
- [Phase 01-foundation]: next-auth pinned to exact version 5.0.0-beta.30; middleware.ts at project root not src/; force-dynamic on auth route
- [Phase 01-foundation 01-02]: PasswordField extracted as co-located client sub-component — keeps login page.tsx as pure server component
- [Phase 01-foundation 01-02]: loginAction re-throws non-AuthError (NEXT_REDIRECT must bubble) — critical Auth.js v5 server action pattern
- [Phase 01-foundation 01-02]: Brand colors applied via inline style props — Tailwind JIT may miss one-off hex values
- [Phase 02-marketing-site]: CSS hover classes in server components — onMouseEnter/onMouseLeave not valid in server component props; use className with style blocks instead
- [Phase 02-marketing-site]: lucide-react installed for marketing site icons (Home, Menu, X, ChevronLeft, ChevronRight)
- [Phase 02-marketing-site 02-02]: nodemailer pinned to ^7.0.7 — v8 conflicts with next-auth@5.0.0-beta.30 peerOptional dep
- [Phase 02-marketing-site 02-02]: useActionState imported from 'react' not 'react-dom' — React 19 canonical API (useFormState removed in React 19)
- [Phase 02-marketing-site 02-02]: Honeypot silent success pattern — bots receive status:success without email sent, preventing bot discovery of rejection
2026-03-19 12:25:02 -06:00
### Pending Todos
None yet.
### Blockers/Concerns
- WFRMLS vendor enrollment takes 2-4 weeks — start process immediately, build Phase 2 listings with mock data while waiting
- Phase 6 (Signing Flow) warrants a /gsd:research-phase before planning — JWT one-time enforcement + ESIGN/UETA audit + mobile touch has edge cases
- DNS (SPF/DKIM/DMARC) for teressacopelandhomes.com must be configured before any signing link reaches a real client (Phase 6 acceptance criterion)
- Exact WFRMLS required IDX disclaimer text must be obtained directly from WFRMLS before listings feature ships (Phase 2)
- WFRMLS vendor enrollment takes 2-4 weeks — start process immediately, build Phase 2 listings with mock data while waiting (moved from Blockers)
2026-03-19 12:25:02 -06:00
## Session Continuity
Last session: 2026-03-19
Stopped at: Completed 02-02-PLAN.md — Contact form: Nodemailer SMTP mailer, Server Action with Zod+honeypot, ContactSection client component
2026-03-19 12:25:02 -06:00
Resume file: None